[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931346":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931346,603,1,"单选题","对工作和工作之间的逻辑关系和工作持续时间都不确定的计划，可同时就费用、时间、效能三方面作综合分析，并对可能发生的风险作概率估计的网络计划技术是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","关键线路法",false,{"key":16,"text":17,"correct":14},"B","计划评审技术",{"key":19,"text":20,"correct":14},"C","图示评审技术",{"key":22,"text":23,"correct":24},"D","风险评审技术",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]