[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931339":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931339,603,2,"多选题","组织流水施工时，划分施工段的原则是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","能充分发挥主导施工机械的生产效率",true,{"key":16,"text":17,"correct":18},"B","根据各专业队的人数随时确定施工段的段界",false,{"key":20,"text":21,"correct":14},"C","施工段的段界尽可能与结构界限相吻合",{"key":23,"text":24,"correct":18},"D","划分施工段只适用于道路工程",{"key":26,"text":27,"correct":14},"E","施工段的数目应满足合理组织流水施工的要求","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]