[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931326":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931326,603,2,"多选题","关于关键线路和关键工作的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","关键线路上相邻工作的时间间隔为零",true,{"key":16,"text":17,"correct":18},"B","关键工作的总时差一定为零",false,{"key":20,"text":21,"correct":18},"C","关键工作的最早开始时间等于最迟开始时间",{"key":23,"text":24,"correct":14},"D","关键线路上各工作持续时间之和最长",{"key":26,"text":27,"correct":14},"E","关键线路可能有多条","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]