[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931324":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931324,603,2,"多选题","在设备工程网络计划的执行过程中，当某项工作进度出现偏差后，出现下列( )情况时，需要调整原进度计划。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设备工程总工期不允许拖延，但工作进度偏差已超过其总时差",true,{"key":16,"text":17,"correct":18},"B","设备工程总工期允许拖延，但工作进度偏差已超过其自由时差",false,{"key":20,"text":21,"correct":14},"C","设备工程总工期允许拖延的时间有限，但实际拖延的时间已超过此限制",{"key":23,"text":24,"correct":14},"D","后续工期不允许拖延，但工作进度偏差已超过其总时差",{"key":26,"text":27,"correct":18},"E","后续工期允许拖延，但工作进度偏差已超过其自由时差","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]