[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931322":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931322,603,1,"单选题","在网络计划工期优化过程中，当出现两条独立的关键线路时，在考虑对质量、安全影响的基础上，优先选择的压缩对象应是这两条关键线路上( )的工作组合。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","资源消耗量之和最小",false,{"key":16,"text":17,"correct":18},"B","直接费用率之和最小",true,{"key":20,"text":21,"correct":14},"C","持续时间之和最长",{"key":23,"text":24,"correct":14},"D","间接费用率之和最小","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]