[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931317":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931317,603,2,"多选题","下列关于横道图与“香蕉”曲线综合比较法的说法，正确的有( )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","能同时反映工程局部和总体进展状况",true,{"key":16,"text":17,"correct":18},"B","只能反映工程局部进展状况",false,{"key":20,"text":21,"correct":18},"C","只能反映工程总体进展状况",{"key":23,"text":24,"correct":14},"D","能反映工程实际与计划总的完成情况",{"key":26,"text":27,"correct":14},"E","横道图和“香蕉”曲线绘制于同一图中","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]