[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931301":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931301,603,1,"单选题","在资源有限-工期最短优化中，在超过资源限量的时段，应将( )，以减少该时段每天资源需要用量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最迟开始时间最大的工作移到最早完成时间最小的工作之后",true,{"key":16,"text":17,"correct":18},"B","最迟开始时间最小的工作移到最早完成时间最大的工作之后",false,{"key":20,"text":21,"correct":18},"C","最迟开始时间最大的工作移到最早完成时间最大的工作之后",{"key":23,"text":24,"correct":18},"D","最迟开始时间最小的工作移到最早完成时间最小的工作之后","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]