[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931295":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931295,603,1,"单选题","下列关于实际进度与计划进度进行比较的横道图比较法的说法，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","能反映工程的关键线路",false,{"key":16,"text":17,"correct":18},"B","适用于各项工作为匀速或非匀速的情况",true,{"key":20,"text":21,"correct":14},"C","能对后期工程的进展进行准确预测",{"key":23,"text":24,"correct":14},"D","需要利用总时差对总体进展进行分析","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]