[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931288,603,1,"单选题","监理工程师控制建设工程进度的技术措施是指( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建立工程进度报告制度及进度信息沟通网络",false,{"key":16,"text":17,"correct":14},"B","协调合同工期与进度计划之间的关系",{"key":19,"text":20,"correct":14},"C","加强风险管理，预测风险因素并提出预防措施",{"key":22,"text":23,"correct":24},"D","审查承包商提交的进度计划，使承包商在合理的状态下施工",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]