[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931287,603,1,"单选题","",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20％W；5％",false,{"key":16,"text":17,"correct":14},"B","21％W；20％",{"key":19,"text":20,"correct":14},"C","25％W；35％",{"key":22,"text":23,"correct":24},"D","26％W；50％",true,"K工作三月份的实际完成工作量为：50%-24%=15%。五月份实际完成工作量是当月计划工作量的(80-65)\u002F(100-70)=50%",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]