[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931286":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":9},931286,603,1,"单选题","",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","左侧，表明此时实际进度比计划进度拖后60t",false,{"key":16,"text":17,"correct":14},"B","右侧，表明此时实际进度比计划进度超前60t",{"key":19,"text":20,"correct":14},"C","左侧，表明此时实际进度比计划进度超前50t",{"key":22,"text":23,"correct":24},"D","右侧，表明此时实际进度比计划进度拖后50t",true,{"id":6,"name":26,"category":27,"favorite":28},"质量、投资、进度控制","建筑工程",0]