[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931280":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931280,603,1,"单选题","在某工程双代号网络计划中，工作M的最早开始时间为第15天，其持续时间为7天。该工作有两项紧后工作，它们的最早开始时间分别为第27天和第30天，最迟开始时间分别为第28天和第33天，则工作M的总时差和自由时差( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","均为5",false,{"key":16,"text":17,"correct":18},"B","分别为6和5",true,{"key":20,"text":21,"correct":14},"C","均为6",{"key":23,"text":24,"correct":14},"D","分别为11和6","本题主要是考六时法计算方法工作M的最迟完成时间应等于其紧后工作最迟开始时间的最小值，所以工作M的最迟完成时间等于[28，33]=28；工作M的总时差为工作M的最迟完成时间减工作M的最早完成时间等于28-(15+7)=6；工作M的自由时差为工作M的紧后工作最早开始时间减工作M的最早完成时间所得之差的最小值：[27-22；30-22]=5。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]