[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931278":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931278,603,1,"单选题","在搭接网络计划中，终点节点一般都表示( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际工作",false,{"key":16,"text":17,"correct":18},"B","虚拟工作",true,{"key":20,"text":21,"correct":14},"C","计划工期",{"key":23,"text":24,"correct":14},"D","实际工期","由于在搭接网络计划中，终点节点一般都表示虚拟工作(其持续时间为零)，故其最早完成时间与最早开始时间相等，且一般为网络计划的计算工期。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]