[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931277":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931277,603,1,"单选题","已知工作A的紧后工作是B和 C，工作B的最迟开始时间为14，最开始时间为10；工作C的最迟完成时间为16，最早完成时间为14；工作A的自由时差为5天，则工作A的总时差为( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","7",false,{"key":20,"text":21,"correct":18},"C","9",{"key":23,"text":24,"correct":18},"D","11","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]