[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931273":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931273,603,1,"单选题","网络计划工期优化的前提是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","满足资源有限条件",false,{"key":16,"text":17,"correct":14},"B","不改变各项工作之间的逻辑关系",{"key":19,"text":20,"correct":14},"C","压缩关键工作工期使之成为非关键工作",{"key":22,"text":23,"correct":24},"D","压缩关键工作工期但保持其仍为关键工作",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]