[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931259":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931259,603,2,"多选题","下列关于施工合同(示范文本)约定的工程计量程序的说法中错误的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人应按专用条款约定的时间向工程师提交已完工程量报告",false,{"key":16,"text":17,"correct":18},"B","工程师接到承包人报告后一个星期内核定工程量，并在计量前48小时通知承包人",true,{"key":20,"text":21,"correct":18},"C","工程师计量时一定要有承包人代表参加，否则计量无效",{"key":23,"text":24,"correct":14},"D","对于承包人超出设计图纸范围和因承包人原因造成返工的工程量，工程师不予计量",{"key":26,"text":27,"correct":14},"E","工程师收到承包人报告后7天内未计量的，从第8天起，承包人报告中开列的工程量视为已被工程师确认","BC","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]