[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931257":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931257,603,2,"多选题","计算项目的挣值(EV)需要依据的数据资料包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","计划工作量",false,{"key":16,"text":17,"correct":18},"B","预算单价",true,{"key":20,"text":21,"correct":18},"C","已完工程量",{"key":23,"text":24,"correct":14},"D","完工预算",{"key":26,"text":27,"correct":14},"E","完工估算","BC","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]