[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931249":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931249,603,1,"单选题","工程总费用由直接费和间接费两部分组成，随着建设工期的缩短，会引起( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接费和间接费同时增加",false,{"key":16,"text":17,"correct":18},"B","直接费增加，间接费减少",true,{"key":20,"text":21,"correct":14},"C","直接费和间接费同时减少",{"key":23,"text":24,"correct":14},"D","直接费减少，间接费增加","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]