[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931245":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931245,603,2,"多选题","设备工程进度监测系统包括( )等过程。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对工程进度计划进行优化",false,{"key":16,"text":17,"correct":18},"B","实际进度数据采集",true,{"key":20,"text":21,"correct":18},"C","实际进度与计划进度对比分析",{"key":23,"text":24,"correct":18},"D","实际进度数据处理",{"key":26,"text":27,"correct":14},"E","更新进度计划","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]