[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931243":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931243,603,2,"多选题","S形曲线图中，纵坐标表示任务量完成情况，任务量可以用( )表达。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","人员使用量",false,{"key":16,"text":17,"correct":18},"B","实物工程量",true,{"key":20,"text":21,"correct":18},"C","工时消耗",{"key":23,"text":24,"correct":18},"D","累计完成任务量百分比",{"key":26,"text":27,"correct":18},"E","费用支出额","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]