[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931233":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":9},931233,603,2,"多选题","",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","以关键节点组成的线路一定为关键线路",false,{"key":16,"text":17,"correct":14},"B","关键节点之间的工作一定为关键工作",{"key":19,"text":20,"correct":21},"C","关键节点的最早时间和最迟时间一定相等",true,{"key":23,"text":24,"correct":14},"D","以关键节点为完成节点的工作的总时差和自由时差一定为零",{"key":26,"text":27,"correct":21},"E","关键工作的总时差和自由时差一定为零","CE",{"id":6,"name":30,"category":31,"favorite":32},"质量、投资、进度控制","建筑工程",0]