[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931215":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931215,603,1,"单选题","在进行“工期固定—资源均衡”优化时，所采取的措施是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","通过改变非关键工作的开始时间",true,{"key":16,"text":17,"correct":18},"B","通过改变关键工作的开始时间",false,{"key":20,"text":21,"correct":18},"C","通过改变非关键工作的完成时间",{"key":23,"text":24,"correct":18},"D","通过改变关键工作的完成时间","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]