[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931212":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931212,603,1,"单选题","在某设备安装工程网络计划中，已知某工作的自由时差为2天，总时差为5天，设备监理工程师在检查进度时发现该工作总时差变为-1天，则说明该工作实际进度比计划进度拖后( )天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","6",true,{"key":23,"text":24,"correct":14},"D","8","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]