[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931210":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931210,603,2,"多选题","在网络计划工期优化过程中，优先选择缩短持续时间的关键工作应是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","持续时间最长的工作",false,{"key":16,"text":17,"correct":14},"B","最早开始时间最短的工作",{"key":19,"text":20,"correct":21},"C","有充足备用资源的工作",true,{"key":23,"text":24,"correct":21},"D","增加所需费用最少的工作",{"key":26,"text":27,"correct":21},"E","对质量和安全影响不大的工作","CDE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]