[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931209":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931209,603,1,"单选题","在某个项目中，存在新老系统切换问题，在设置项目计划网络图时，新系统上线和老系统下线之间应设置成( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","结束到开始(FS型)关系",false,{"key":16,"text":17,"correct":14},"B","结束到结束(FF型)关系",{"key":19,"text":20,"correct":14},"C","开始到开始(SS型)关系",{"key":22,"text":23,"correct":24},"D","开始到结束(SF型)关系",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]