[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931204":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931204,603,1,"单选题","双代号网络计划的计算工期应等于其所有最后结束工作的( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最早完成时间最小值",false,{"key":16,"text":17,"correct":14},"B","最迟完成时间最小值",{"key":19,"text":20,"correct":21},"C","最早完成时间最大值",true,{"key":23,"text":24,"correct":14},"D","最迟完成时间平均值","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]