[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931202,603,1,"单选题","在设备工程进度管理的动态循环过程中，设备监理工程师通常通过( )方法决定是否更新进度计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","逻辑关系分析",false,{"key":16,"text":17,"correct":14},"B","三时估计",{"key":19,"text":20,"correct":21},"C","偏差分析",true,{"key":23,"text":24,"correct":14},"D","因果关系分析","进度调整当偏差较大必须调整进度时，应及时更新进度计划。要求出现进度偏差的承包商更新其进度计划和提出保证按进度计划执行的可行措施，同时对受影响的总进度计划进行更新。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]