[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931192":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931192,603,2,"多选题","过程失效模式及影响分析(PFME A)的作用包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","确定与产品相关的过程失效模式",true,{"key":16,"text":17,"correct":14},"B","评价失效模式对顾客的潜在影响",{"key":19,"text":20,"correct":14},"C","确定失效起因，减少失效",{"key":22,"text":23,"correct":24},"D","确定失效过程的最小割集",false,{"key":26,"text":27,"correct":14},"E","根据失效模式的级别建立纠正措施的优选体系","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]