[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931190":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931190,603,1,"单选题","在某工程网络计划中，工作M有2项紧前工作K、L，它们的最早开始时间分别为第4天和第6天，持续时间分别为4天和7天，则工作K、M的时间间隔LAGK，M为( )天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2；",false,{"key":16,"text":17,"correct":14},"B","3；",{"key":19,"text":20,"correct":14},"C","4；",{"key":22,"text":23,"correct":24},"D","5；",true,"LAGk-m=ESm-EFk=(6+7)-(4+4)=13-8=5",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]