[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931189":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931189,603,2,"多选题","在出现进度延误时，保持进度计划工期不变的技术措施调整方法可能有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","改变关键工作间的逻辑关系",true,{"key":16,"text":17,"correct":18},"B","增加非关键工作上资源量",false,{"key":20,"text":21,"correct":18},"C","缩短非关键工作的持续时间",{"key":23,"text":24,"correct":14},"D","压缩关键工作的持续时间",{"key":26,"text":27,"correct":18},"E","改变非关键工作间的逻辑关系","AD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]