[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931184":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931184,603,2,"多选题","挣值管理主要通过( )关键参数来衡量项目的实施状态。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","成本偏差",false,{"key":16,"text":17,"correct":18},"B","计划价值",true,{"key":20,"text":21,"correct":18},"C","挣值",{"key":23,"text":24,"correct":18},"D","实际成本",{"key":26,"text":27,"correct":14},"E","进度偏差","BCD","挣值管理主要通过计划价值(PV)、挣值(EV)和实际成本(AC)三个关键参数来衡量项目的实施状态。这些指标实际上都是关于进度与成本的函数。",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]