[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931183":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":9},931183,603,1,"单选题","",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","C工作实际进度拖后2周，影响工期2周",false,{"key":16,"text":17,"correct":14},"B","D工作实际进度拖后2周，影响工期l周",{"key":19,"text":20,"correct":21},"C","D工作实际进度拖后3周，影响工期2周",true,{"key":23,"text":24,"correct":14},"D","E工作实际进度拖后1周，不影响工期",{"id":6,"name":26,"category":27,"favorite":28},"质量、投资、进度控制","建筑工程",0]