[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931174":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931174,603,1,"单选题","",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","虽然工作E拖后1周，但对后续工作及总工期均不产生影响；",false,{"key":16,"text":17,"correct":14},"B","由于工作C拖后1周，因而使工期延长1周；",{"key":19,"text":20,"correct":14},"C","虽然工作D拖后2周，但对后续工作及总工期均不产生影响；",{"key":22,"text":23,"correct":24},"D","虽然工作C拖后1周，但并不影响其后续工作的正常进行。",true,"C工作为关键工作，C工作拖后，必影响其后续工作。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]