[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931172":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931172,603,1,"单选题","在双代号网络计划中，某工作有四项紧后工作，它们的最迟开始时间分别是第13天、第15天、第19天和第20天，则该工作的最迟完成时间是第( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","13",true,{"key":16,"text":17,"correct":18},"B","15",false,{"key":20,"text":21,"correct":18},"C","19",{"key":23,"text":24,"correct":18},"D","20","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]