[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931167":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":9},931167,603,1,"单选题","",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作B不影响工期，工作C影响工期1天",false,{"key":16,"text":17,"correct":14},"B","工作 A.C均不影响工期工作",{"key":19,"text":20,"correct":21},"C","C不影响工期，工作B影响工期1天",true,{"key":23,"text":24,"correct":14},"D","工作A进度正常，工作C各影响工期1天",{"id":6,"name":26,"category":27,"favorite":28},"质量、投资、进度控制","建筑工程",0]