[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931166":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931166,603,1,"单选题","设备监理工程师对详细进度计划进行审核的依据是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理合同",false,{"key":16,"text":17,"correct":18},"B","业主与承包商签订的合同",true,{"key":20,"text":21,"correct":14},"C","设计图纸",{"key":23,"text":24,"correct":14},"D","国家的法律.法规及相关的规范.规程","4.审核设备工程详细进度计划设备监理工程师根据业主和承包商签订的合同对进度计划进行审核，审核的主要内容有：①进度安排是否满足合同规定的开竣工日期；②该进度计划是否与其他单位的进度计划协调一致；③设备的工序安排是否合理，是否符合相关标准和程序要求；④外购分包计划和原材料采购计划能否保证进度计划的实现；⑤人力资源.设备资源安排是否满足进度计划要求；⑥各项工作的进度安排是否合理可行；⑦进度计划的安排是否满足连续性.均衡性的要求。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]