[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931161":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931161,603,1,"单选题","在雇用了总承包商的情况下，设备监理工程师需对设备工程总进度计划进行( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制",false,{"key":16,"text":17,"correct":18},"B","审核",true,{"key":20,"text":21,"correct":14},"C","编制或审核",{"key":23,"text":24,"correct":14},"D","修改","在雇用了总承包商的情况下，由总承包商编制设备工程的总进度计划，设备监理工程师只需负责审核。在雇用多个承包商的情况下，设备监理工程师需要负责编制设备工程总进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]