[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931156":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931156,603,1,"单选题","在网络计划工期优化过程中，当出现多条关键线路时，为使工期缩短，应( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压缩所需资源总量最少的一条关键线路",false,{"key":16,"text":17,"correct":18},"B","将各关键线路持续时间压缩为同一数值",true,{"key":20,"text":21,"correct":14},"C","压缩对质量和安全影响不大的部分关键线路",{"key":23,"text":24,"correct":14},"D","对不同的关键线路持续时间压缩不同的数值","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]