[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931155,603,1,"单选题","某双代号网络计划中(以天为时间单位)，工作K的最早开始时间为6，工作持续时间为4；工作M的最迟完成时间为22，工作持续时间为10；工作N的最迟完成时间为20，工作持续时间为5。己知工作K只有M、N两项紧后工作，工作K的总时差为( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","5",{"key":23,"text":24,"correct":18},"D","6","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]