[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931151":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931151,603,1,"单选题","根据某设备工程网络计划计算，阀门安装工作的总时差为5天，自由时差为2天，该工作实际进度比计划拖后4天，表明( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","影响总工期l天",false,{"key":16,"text":17,"correct":18},"B","影响后续工作但不影响总工期",true,{"key":20,"text":21,"correct":14},"C","不影响后续工作",{"key":23,"text":24,"correct":14},"D","既不影响后续工作也不影响总工期","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]