[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931147":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931147,603,1,"单选题","某混凝土工程，9月份计划工程量为5000m3，计划单价为400元／m3；而9月份实际完成工程量为4000m3，实际单价为410元／m3，则该工程9月份的进度偏差为( )万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","-36",false,{"key":16,"text":17,"correct":14},"B","36",{"key":19,"text":20,"correct":21},"C","40",true,{"key":23,"text":24,"correct":14},"D","41","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]