[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931145":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931145,603,1,"单选题","工作和工作之间的逻辑关系确定，但工作的持续时间不确定，应进行时间参数估算，并对按期完成任务的可能性做出评价的网络计划技术是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键线路法",false,{"key":16,"text":17,"correct":18},"B","计划评审技术",true,{"key":20,"text":21,"correct":14},"C","图示评审技术",{"key":23,"text":24,"correct":14},"D","风险评审技术","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]