[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931139,603,1,"单选题","当利用S形曲线进行实际进度与计划进度比较时，如果检查日期实际进展点落在计划S形曲线的右侧，则该实际进展点与计划S形曲线的水平跟离表示工程项目( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际进度超前的时间",false,{"key":16,"text":17,"correct":18},"B","实际进度拖后的时间",true,{"key":20,"text":21,"correct":14},"C","实际超额完成的任务量",{"key":23,"text":24,"correct":14},"D","实际拖欠的任务量","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]