[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931130":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931130,603,2,"多选题","工程网络计划的计算工期等于( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单代号网络图中终点节点所代表工作的最早完成时间",true,{"key":16,"text":17,"correct":18},"B","单代号网络图中终点节点所代表工作的最晚完成时间",false,{"key":20,"text":21,"correct":14},"C","双代号网络图中以终点节点为完成节点工作的最早完成时间的最大值",{"key":23,"text":24,"correct":18},"D","双代号网络图中以终点节点为完成节点工作的最晚完成时间的最大值",{"key":26,"text":27,"correct":14},"E","时标网络计划中最后一项关键工作的最早完成时间","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]