[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931126":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931126,603,2,"多选题","某设备工程采用总承包(EP C)模式发包，在设备工程设计过程中，设备监理工程师进行进度管理应审核的承包商文件包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包商设计工作进度计划",true,{"key":16,"text":17,"correct":18},"B","设备制造进度计划",false,{"key":20,"text":21,"correct":14},"C","设计变更工作进度计划",{"key":23,"text":24,"correct":14},"D","设计工期索赔报告",{"key":26,"text":27,"correct":18},"E","全系统设备调试进度计划","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]