[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931124":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931124,603,2,"多选题","按检验的时间节点分，检验和试验包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","全数检验",false,{"key":16,"text":17,"correct":18},"B","进货检验",true,{"key":20,"text":21,"correct":18},"C","过程检验",{"key":23,"text":24,"correct":18},"D","最终检验",{"key":26,"text":27,"correct":14},"E","抽样检验","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]