[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931121":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931121,603,1,"单选题","组织实施初始状态评审之后，根据评审结果，结合组织现有的资源以及现有的技术水平，进行管理体系的( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","领导决策",false,{"key":16,"text":17,"correct":14},"B","贯标培训",{"key":19,"text":20,"correct":14},"C","成立工作组",{"key":22,"text":23,"correct":24},"D","整体策划和设计",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]