[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931118":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931118,603,2,"多选题","某设备工程进度计划在执行过程中，已知工作M的总时差和自由时差分别为6天和3天，在进行进度检查时，发现该工作比原计划拖延了4天，则此时的进度状况是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总工期将会延长",false,{"key":16,"text":17,"correct":18},"B","后续工作受到影响",true,{"key":20,"text":21,"correct":14},"C","工作M总时差减少3天",{"key":23,"text":24,"correct":18},"D","工作M尚有总时差2天",{"key":26,"text":27,"correct":18},"E","紧后工作最早开始时间向后推迟1天","BDE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]