[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931115,603,1,"单选题","在建设工程进度控制计划体系中，具体安排单位工程的开工日期和竣工日期的计划是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程项目进度平衡表",false,{"key":16,"text":17,"correct":14},"B","单位工程施工进度计划‘",{"key":19,"text":20,"correct":14},"C","工程项目前期工作计划",{"key":22,"text":23,"correct":24},"D","工程项目总进度计划",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]