[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931105":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931105,603,1,"单选题","在某工程双代号网络计划中，如果以某关键节点为完成节点的工作有2项，则该两项工作( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全部为关键工作",false,{"key":16,"text":17,"correct":18},"B","至少有一项为关键工作",true,{"key":20,"text":21,"correct":14},"C","自由时差相等",{"key":23,"text":24,"correct":14},"D","总时差相等","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]